Project Name: Freight Rail Track Slab Upgrade

 

Location: DP World Port Botany Terminal

 

Client: Downer Australia

 

Civilcraft was engaged by Downer Australia to assist with the construction of a new freight rail track upgrade. This upgrade added another rail siding to the DP World Terminal which will allow in more freight to be transported by rail. These works involved the installation of a new stormwater system, the construction of a basecourse layer and concrete pavement works.

 

SCOPE OF WORKS

- Installation of dewatering spears to lower ground water table from the workface

- Excavation of stormwater pits and install shoring boxes

- Excavation of trenches to all for stormwater pipes and precast pits and riser installations

- Backfilling of trenches with premixed concrete to underside of subbase layer

- Importing, spreading and compacting of roadbase layer and compaction testing

- Installation of ballast cages on top of stormwater pits

- Pouring of 50mm concrete blinding layer

- Installation and tying of steel reinforcement

- Installation of sleepers by others

- Forming and pouring of concrete pavement and transition slabs with upturns

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 